Cost-Plus-Percentage Contract

An agreement on a construction project where the contractor earns a specified percentage profit over the actual costs incurred. This contract type is considered suboptimal due to reduced incentives for cost control. An alternative approach is the cost-plus-fixed-fee contract.

Cost-Plus-Percentage Contract

Definition

A cost-plus-percentage contract is a type of agreement used predominantly in construction projects whereby the contractor is reimbursed for all actual costs incurred and, in addition, receives a pre-determined percentage of these costs as profit. This arrangement means that the higher the cost of the project, the greater the contractor’s profit, thus potentially reducing any incentive to minimize expenses.

Key Characteristics

  • Reimbursement of Actual Costs: Contractor is reimbursed for all direct costs (materials, labor, equipment, etc.) and indirect costs (overheads, administrative expenses, etc.).
  • Percentage Profit: The profit is determined as a fixed percentage of the project’s total actual cost.
  • Risk and Incentive: Contractor’s risk is minimized, but there is little incentive to control or reduce project expenses.

Examples

  1. Commercial Building Construction: A contractor building a commercial office complex is reimbursed for all construction-related expenses plus a 10% profit margin on the total costs.
  2. Government Projects: Public sector projects can sometimes use such contracts, despite their potential for cost overruns if not carefully monitored.
  3. Research and Development Projects: Specialized R&D projects where the costs can be highly variable and difficult to estimate upfront.

Frequently Asked Questions (FAQ)

Q: What makes cost-plus-percentage contracts less favorable? A: They discourage the contractor from managing costs efficiently because higher project costs result in higher profits, leading to potential cost overruns.

Q: What is an alternative to cost-plus-percentage contracts? A: A cost-plus-fixed-fee contract is a better alternative where the contractor receives a fixed fee in addition to the reimbursement of actual costs, aligning incentives for cost control.

  • Cost-Plus-Fixed-Fee Contract: An agreement where the contractor is reimbursed for all actual costs plus a fixed fee which does not vary with the project cost, encouraging cost control.
  • Lump-Sum Contract: A contract where the contractor agrees to complete the project for a fixed total price, thereby assuming the risk of cost overruns.
  • Time and Materials Contract: The contractor is paid for the time spent and materials used, suitable for projects where the scope is not well-defined.
  • Guaranteed Maximum Price Contract: The contractor is reimbursed for costs up to a maximum price, providing protection against cost overruns.

Online References

Suggested Books

  1. “Construction Contracts: Law and Management” by John Murdoch and Will Hughes - Provides in-depth coverage of various construction contracts and their legal implications.
  2. “Construction Project Management: A Practical Guide to Field Construction Management” by S. Keoki Sears, Glenn A. Sears, and Richard H. Clough - A guide to managing construction projects effectively.
  3. “Handbook of Construction Contracting: Plans, Speculations, Building” by Jack P. Jones - Offers practical advice on decision-making and contract management in construction.

Fundamentals of Cost-Plus-Percentage Contract: Contract Management Basics Quiz

### What is a core feature of the cost-plus-percentage contract? - [x] The contractor is paid a specified percentage profit over actual costs. - [ ] The contractor is paid a lump sum amount for the project. - [ ] The profit percentage is variable. - [ ] The contractor is held liable for cost overruns. > **Explanation:** In a cost-plus-percentage contract, the contractor's profit is tied to the actual costs incurred, with profit calculated as a percentage of these costs. ### What is a major drawback of cost-plus-percentage contracts? - [ ] They are easier to manage. - [x] They provide little incentive to control costs. - [ ] They eliminate the risk for the contractor. - [ ] They foster better client-contractor relationships. > **Explanation:** The main disadvantage of cost-plus-percentage contracts is that they do not incentivize the contractor to keep costs low, potentially leading to higher total project expenses. ### Which type of contract is recommended as a better alternative to cost-plus-percentage contracts? - [x] Cost-Plus-Fixed-Fee Contract - [ ] Lump-Sum Contract - [ ] Unit Price Contract - [ ] Time and Materials Contract > **Explanation:** Cost-plus-fixed-fee contracts are preferred over cost-plus-percentage contracts because they offer a fixed profit fee, encouraging the contractor to control costs better. ### What does a cost-plus-percentage contract lack in terms of cost management? - [ ] Project scope definition - [x] Strong incentive for cost efficiency - [ ] Reimbursement of costs - [ ] Payment schedule flexibility > **Explanation:** The structure of cost-plus-percentage contracts provides little motivation for the contractor to manage or reduce costs, lacking a strong incentive for cost efficiency. ### How does a cost-plus-fixed-fee contract differ from a cost-plus-percentage contract? - [ ] It does not reimburse actual costs. - [ ] It provides a percentage of the total project cost as profit. - [x] It offers a fixed fee irrespective of the project costs. - [ ] It is typically used for personal construction projects. > **Explanation:** In a cost-plus-fixed-fee contract, the contractor is paid a fixed fee for profit, unrelated to the actual costs, promoting better cost management. ### Which type of project might be less suitable for a cost-plus-percentage contract? - [x] Projects with well-defined scopes and budgets - [ ] High-uncertainty R&D projects - [ ] Government infrastructure projects - [ ] Complex renovation projects > **Explanation:** Projects with well-defined scopes and budgets are less suitable for cost-plus-percentage contracts, as the lack of cost control incentives can lead to budget overruns, better managed with fixed-fee or lump-sum contracts. ### What does a lump-sum contract entail? - [x] A fixed total price for the entire project. - [ ] Profit based on a percentage of project costs. - [ ] Reimbursement of time and materials used. - [ ] Costs plus a variable fee based on performance. > **Explanation:** In a lump-sum contract, a fixed total price is agreed upon for the entire project, transferring cost overrun risk to the contractor. ### Under which contract type is the contractor guaranteed a maximum payment cap? - [ ] Cost-Plus-Percentage Contract - [ ] Time and Materials Contract - [x] Guaranteed Maximum Price Contract - [ ] Lump-Sum Contract > **Explanation:** A Guaranteed Maximum Price (GMP) contract caps the maximum payment to the contractor, protecting against cost overruns above the agreed maximum price. ### In cost-plus-percentage contracts, what is an indirect cost the contractor might be reimbursed for? - [ ] Material costs - [ ] Hourly labor wages - [x] Overheads and administrative expenses - [ ] Equipment purchase > **Explanation:** Indirect costs, such as overheads and administrative expenses, are reimbursable under cost-plus-percentage contracts, along with direct project costs. ### Which factor largely determines the profit for the contractor in a cost-plus-percentage contract? - [x] The total actual cost of the project - [ ] The project's completion time - [ ] The initial project budget - [ ] The contractor’s previous project performances > **Explanation:** The contractor's profit in a cost-plus-percentage contract is a specified percentage of the total actual cost incurred on the project.

Thank you for exploring the fundamentals of cost-plus-percentage contracts and delving into our quiz. Continue enhancing your expertise in the domain of contract management!